We Praise God for His provision and grace and your support as we could start the much-needed work at the Dighi Boys’ Hostel on 13th January 2025.

Progress Report

  1. Priority Areas to start the work:
    The kitchen, the store, and the dormitory adjacent to the store were identified as our highest priority to start the work. This particular structure was at risk to collapse due to its original construction without proper foundations.
  1. Demolition and Clearing: The labourers carefully dismantled the water tank, removed the roof, and began breaking the sidewalls of the dormitory. This delicate process has been carried out to prevent any damage to the surrounding areas.
  1. Current Status:
    As of today, the roof has been fully removed, and the labourers are in the final stages of breaking the sidewalls. The foundation work is set to begin shortly, with a focus on completing this phase with speed and care.
  1. Temporary Arrangements:
    The children residing in the affected dormitory have been safely relocated. A temporary kitchen shed has been set up to ensure uninterrupted meal preparation during the construction period.

Timeline and Goals:

Our team is working diligently to complete the work within the planned timeline. We aim to provide a safe and durable environment that will serve the children for many years to come.

Prayer Requests:

We humbly ask for your continued prayers for:

  • The safety of the labourers as they carry out the construction work.
  • Timely completion of the project without any unforeseen delays.
  • The children and staff to adjust smoothly during this transition period.

We give all glory to God for His guidance and provision thus far. We trust that He will complete the good work He has begun in this place, equipping us to serve the children with excellence and love.

In His Service,
Subhash & Raja